BSV07102 Surveying 1
COURSEWORK 2
Check before you submit. Get Turnitin Score Report in 15 Minutes.
Don't risk the 'Red' score. Get the exact same Turnitin report your professor uses. Join 50,000+ students who submitted their essays with confidence this semester.
Q 1 Two existing manholes, A and B are to be connected by a sewer. The plan length AB is 140.000m
The line of the sewer was established by means of pegs at 20m intervals. The peg tops were levelled by taking a run of levels starting on TBM1 and finishing on TBM2. The results are shown in Table Q.1. The excavation for the sewer is to be monitored using profiles and a 2.5m traveller.
- Draw up a suitable level book page and reduce the levels carrying out relevant arithmetic checks. (10)
- Calculate the gradient of the pipe. (3)
- Calculate the required heights of the profiles above the tops of the pegs. (4)
(Total 17)
| BS | IS | FS | Distance from
Manhole A |
Remarks |
| 1.926 | TBM1
(RL 95.249 AOD) |
|||
| 2.989 | 0 | Invert manhole A | ||
| 1.744 | 20 | Top of Peg 1 | ||
| 1.308 | 1.873 | 40 | Top of Peg 2 | |
| 1.481 | 60 | Top of Peg 3 | ||
| 1.746 | 80 | Top of Peg 4 | ||
| 0.924 | 2.088 | 100 | Top of Peg 5 | |
| 1.062 | 120 | Top of Peg 6 | ||
| 1.598 | 140 | Invert Manhole B | ||
| 2.206 | TBM 2
(RL 93.240m AOD) |
Table Q 1
Q.2
An anti-clockwise closed traverse 9, 10, 11,12,9 was used as the controlling framework for a topographical survey of a small area of ground.
Table Q.2 provides details of the horizontal angle measurements recorded on two faces during the traverse stage, along with the computed horizontal distances.
| Instrument
Station |
Target
Station |
Face 1
Hor. Angle |
Face 2
Hor. Angle |
Line | Mean
Distance |
| 9 | 12
10 |
00°00′00″
100°08′20″ |
179°59′58″
280°08′14″ |
9-10 | 60.025m |
| 10 | 9
11 |
00°00′00″
50°56′54″ |
180°00′05″
230°56′46″ |
10-11 | 21.134m |
| 11 | 10
12 |
00°00′00″
131°07′41″ |
179°59′56″
311°07′40″ |
11-12 | 49.995m |
| 12 | 11
9 |
00°00′00″
77°46′38″ |
180°00′06″
257°46′45″ |
12-9 | 18.512m |
Table Q.2
The W.C.B. of the line 9-10 was determined accurately as 71°10′34″ with the coordinates of 9 being 1039.712m E, 1022.578m N.
- Determine the mean horizontal angle recorded at each instrument station. (7)
- Using Worksheet Q.2 complete and adjust the traverse. (8)
- Comment on the accuracy of the results. (2)
(Total 17)
Q3
Four corners V,X,Y and Z of a proposed Telephone mast base are to be set out initially from Station “A” by angle and distance and then checked by intersection from station “D”.
The stations and the detail points are all based on the same coordinate system and are given in the table below.
| Station | Easting | Northing |
| A | 1000.000 | 1000.000 |
| D | 984.396 | 994.269 |
| Detail points | ||
| V | 994.478 | 999.223 |
| X | 994.478 | 1000.723 |
| Y | 991.478 | 1000.723 |
| Z | 991.478 | 999.223 |
- Describe with full calculations a method of setting out the 4 points. (9)
- Describe a method of checking the position of the points again showing all working.
(7)
Total (16)
Welcome to our trusted essay writing website with track record among students. We specialize in connecting students in need of high-quality essay assistance with skilled writers who can deliver just that. Explore the ratings of our essay writers and choose the one that best aligns with your requirements. When you rely on our online essay writing service, rest assured that you will receive a top-notch, plagiarism-free A-level paper. Our experienced professionals write each paper from scratch, carefully following your instructions. Request a paper from us and experience 100% originality.